Progress

Keep up to date with the progress of the Sports Village...

Quick Links:

May 2005

  • Enabling drainage works completed
  • Contractor takes possession of the site
  • Contractor mobilises - sets up the compound, on-site offices and assembles teams

back to top

June 2005

  • Contractor completes mobilisation
  • Detailed programme of works finalised
  • 29th June - press launch of project

back to top

July 2005

  • Demolition of the pavilion
  • Terracing of the pitch areas begins
  • Substructure construction continues with foundations of the new sports hall laid
  • Specialist pitch contractor begins on new pitch drainage

back to top

August 2005

  • Building complex slab re-inforced and completed
  • Steel frame erected
  • Construction of internal load bearing walls begins
  • Car park works commence
  • Work on pitches continues - excavation, drainage

back to top

September 2005

  • Work commences on changing block
  • Foundation work complete
  • Roof decking to main sports hall complete
  • Cycle track takes shape

back to top

October 2005

  • Highway improvements - work to new roundabout commences
  • New footpaths created in woodland
  • Car park areas developed
  • Lighting for cycle track erected
  • Construction of grandstand commences
  • Mechanical and Engineering first fit begins

back to top

November 2005

  • Erection of carpark lighting commences
  • Carpentry works continue towards completion
  • Underfloor heating and insulation installed
  • Artificial pitch laid

back to top

December 2005

  • Martial Arts Centre carpark resurfaced
  • Completion of main highway works
  • Footpath the west of site completed and released for public use
  • Internal plaster work commences
  • Christmas shutdown

back to top

January 2006

  • Christmas shutdown
  • Cladding works towards completion
  • Plaster work progresses
  • Mechanical and electrical works progress

back to top

February 2006

  • Squash courts fitted out
  • Construction of ramps to pitch areas begins
  • Tiling in shower areas commences

back to top

March 2006

  • Reception desk installed
  • Construction of climbing wall begins
  • Terrace balustrading erected
  • Cycle track tarmacced
  • Sports hall floor laid
  • Landscaping begins
  • Kitchen area tiled
  • Vanity units fitted
  • Shower areas tiled

back to top

April 2006

  • Lights fitted in cafe bar area
  • Climbing wall balustrade fitted
  • Vinyl laid
  • Sports hall equipment fitted
  • Lockers installed

back to top