Progress
Keep up to date with the progress of the proposed New Entertainment Venue...
Quick Links:

May 2005
- Public Information Events held at the Guildhall
- Site Investigation survey
- Ongoing design - preparation for planning submission (RIBA Stage D)
June 2005
- Public Information Event held at the Music Hall
- Correlation of public survey results
- Submission of planning application
- Completion of design to RIBA Stage D
July 2005
- Site clearance
- Compilation of Site Investigation Report
- Continued consultation for planning application process
- Design work to RIBA Stage E

August 2005
- Site clearance complete
- Continued consultation for planning application process
- Design work for planning application
September 2005
- Further design work and preparation of planning applications
October 2005
- Main and substation application submitted
- Planning permission granted for both applications with conditions
November 2005
- Government of West Midlands approve planning submission
- Change of procurement route to Design and Build contract
- OJEU issued for main contractor
December 2005
- Expressions of interest recieved after publication of OJEC notice
- Shortlist of ineterested contractors drawn up
January 2006
- Shortlisted contractors invited to interview
February 2006
- Preparation of tender documents
March 2006
- Archaeological Investigation
- Archaeology public open days
April 2006
May 2006
- Designs are progressed
- Final pre-construction programme confirmed
- Work begins on new Autotyres depot to relocate existing business
June 2006
- Work to designs continue
- All land ownership items concluded
- Pre-contract ground works completed
July 2006
- New planning application submitted
- NEV named - Theatre Severn
- Final archaeology reports completed
August 2006
- Internal layouts signed off by users
- Sample boards constructed on site to choose brick types

September 2006
- Revised planning application submitted
- Planning granted
October 2006
- Contract signed
November 2006
- Contractor takes possession of the site
- Construction commences
- Webcam goes live
December 2006
- Construction of new substation commences
- Test piling begins
- Autotyres relocate to Nettles Lane
January 2007
- Site clearance completed
- Reduced level dig commenced
- 1st stage piling complete
- Substation brickwork and blockwork complete
- Highway works commenced
February 2007
- Reduced level dig completed
- Substation roof installed
- Steelwork commenced
March 2007
- Studio theatre and dance studio pile caps and ground beams completed
- Steel frame to studio theatre completed
- Substation switchgear installed
April 2007
- Under slab drainage to studio theatre completed
- Fly tower and main auditorium pile caps and ground beams completed
May 2007
- Storm water drainage tank installed
- Perimeter drainage works commenced
- First floor slab to studio theatre completed
- Blockwork to studio theatre commenced
- Chapel interior stripped out
June 2007
- Archaeology dig completed
- Piling rig back on site to complete piling
- New photographs
July 2007
- Piling completed
- Tower crane on site to erect remaining steelwork
August 2007
- Upper level floor slabs under construction
September 2007
- Studio theatre. dance studio and back of house lift pits installed
- Main auditorium scenery hoist base and walls constructed
- Orchestra pit base and walls constructed
October 2007
November 2007
- External elevations prepared for timber cladding
- Roofing works to flytower complete
December 2007

January 2008
- Flytower zinc cladding work begins
February 2008
- Riverside curtain walling complete
- Window installation begins
- Flytower cladding complete
March 2008
- Internal brickwork complete
April 2008
- Auditorium zinc cladding begins
May 2008
- Roofing works to flytower complete
- Dry lining to studio theatre begins
- Theatre machinery installation commences in studio theatre
- Tower crane removed from site
June 2008
- Timber cladding works to studio theatre complete
- Auditorium drum wall complete
- Glazing to dance studio complete
- Roofing works to dance studio complete
- Installation of main auditorium scenery hoist commences
- Internal ceiling work commences
- Work to orchestra pit begins
July 2008
- M&E first fix complete
- Timber floors to stalls complete
- Orchestra pit lift installed
August 2008
- Studio theatre counterweight system complete
- High level ceiling and decoration works in main auditorium complete
- Chapel roof tiling complete
September 2008
- Final floor finish work commences
- WC areas complete
- Studio theatre seating installed