Progress

Keep up to date with the progress of the proposed New Entertainment Venue...

Quick Links:

May 2005 January 2006 January 2007 January 2008
June 2005 February 2006 February 2007 February 2008
July 2005 March 2006 March 2007 March 2008
August 2005 April 2006 April 2007 April 2008
September 2005 May 2006

May 2007

May 2008
October 2005 June 2006 June 2007  June 2008
November 2005 July 2006 July 2007 July 2008
December 2005 August 2006 August 2007 August 2008
September 2006 September 2007 September 2008
October 2006 October 2007
November 2006 November 2007
December 2006 December 2007

 

May 2005

  • Public Information Events held at the Guildhall
  • Site Investigation survey
  • Ongoing design - preparation for planning submission (RIBA Stage D)

back to top

 

June 2005

  • Public Information Event held at the Music Hall
  • Correlation of public survey results
  • Submission of planning application
  • Completion of design to RIBA Stage D

back to top

 

July 2005

  • Site clearance
  • Compilation of Site Investigation Report
  • Continued consultation for planning application process
  • Design work to RIBA Stage E

back to top

 

August 2005

  • Site clearance complete
  • Continued consultation for planning application process
  • Design work for planning application 

back to top

 

September 2005

  • Further design work and preparation of planning applications

back to top

 

October 2005

  • Main and substation application submitted
  • Planning permission granted for both applications with conditions

back to top

 

November 2005

  • Government of West Midlands approve planning submission
  • Change of procurement route to Design and Build contract
  • OJEU issued for main contractor

back to top

 

December 2005

  • Expressions of interest recieved after publication of OJEC notice
  • Shortlist of ineterested contractors drawn up

back to top

 

January 2006

  • Shortlisted contractors invited to interview

back to top

 

February 2006

  • Preparation of tender documents

back to top

 

March 2006

back to top

 

April 2006

back to top

 

May 2006

  • Designs are progressed
  • Final pre-construction programme confirmed
  • Work begins on new Autotyres depot to relocate existing business

back to top

 

June 2006

  • Work to designs continue
  • All land ownership items concluded
  • Pre-contract ground works completed

back to top

 

July 2006

back to top

 

August 2006

  • Internal layouts signed off by users
  • Sample boards constructed on site to choose brick types

back to top

 

September 2006

back to top

 

October 2006

  • Contract signed

back to top

 

November 2006

  • Contractor takes possession of the site
  • Construction commences
  • Webcam goes live

back to top

 

December 2006

  • Construction of new substation commences
  • Test piling begins
  • Autotyres relocate to Nettles Lane

back to top

 

January 2007

  • Site clearance completed
  • Reduced level dig commenced
  • 1st stage piling complete
  • Substation brickwork and blockwork complete
  • Highway works commenced

back to top

 

February 2007

  • Reduced level dig completed
  • Substation roof installed
  • Steelwork commenced

back to top

 

March 2007

  • Studio theatre and dance studio pile caps and ground beams completed
  • Steel frame to studio theatre completed
  • Substation switchgear installed

back to top

 

April 2007

  • Under slab drainage to studio theatre completed
  • Fly tower and main auditorium pile caps and ground beams completed

back to top

 

May 2007

  • Storm water drainage tank installed
  • Perimeter drainage works commenced
  • First floor slab to studio theatre completed
  • Blockwork to studio theatre commenced
  • Chapel interior stripped out

back to top

 

June 2007

  • Archaeology dig completed
  • Piling rig back on site to complete piling
  • New photographs

back to top

 

July 2007

  • Piling completed
  • Tower crane on site to erect remaining steelwork

back to top

 

August 2007

  • Upper level floor slabs under construction

back to top

 

September 2007

  • Studio theatre. dance studio and back of house lift pits installed
  • Main auditorium scenery hoist base and walls constructed
  • Orchestra pit base and walls constructed

back to top

 

October 2007

back to top

 

November 2007

  • External elevations prepared for timber cladding
  • Roofing works to flytower complete

back to top

 

December 2007

Main stage

back to top

 

January 2008

  • Flytower zinc cladding work begins

 

back to top

 

February 2008

  • Riverside curtain walling complete
  • Window installation begins
  • Flytower cladding complete

 

back to top

 

March 2008

  • Internal brickwork complete

 

back to top

 

April 2008

  • Auditorium zinc cladding begins

 

back to top

 

May 2008

  • Roofing works to flytower complete
  • Dry lining to studio theatre begins
  • Theatre machinery installation commences in studio theatre
  • Tower crane removed from site

back to top

 

June 2008

  • Timber cladding works to studio theatre complete
  • Auditorium drum wall complete
  • Glazing to dance studio complete
  • Roofing works to dance studio complete
  • Installation of main auditorium scenery hoist commences
  • Internal ceiling work commences
  • Work to orchestra pit begins

back to top

 

July 2008

  • M&E first fix complete
  • Timber floors to stalls complete
  • Orchestra pit lift installed

back to top

 

August 2008

  • Studio theatre counterweight system complete
  • High level ceiling and decoration works in main auditorium complete
  • Chapel roof tiling complete

back to top

 

September 2008

  • Final floor finish work commences
  • WC areas complete
  • Studio theatre seating installed

back to top