Whitehouse Gardens
This project has now been completed. 5 of the properties are now being managed by Severnside Housing Association. The remaining property is being used by SABC for temporary accommodation.
If you would like further information about the construction of the houses please contact the project team by emailing projects@shrewsbury.gov.uk.
For information about social housing please contact Severnside Housing Association by emailing enquiries@severnsidehousing.co.uk or view their webpage at www.severnsidehousing.co.uk.
For information about temporary accommodation please contact SABC's Housing Options team by emailing housingoptions@shrewsbury.gov.uk or viewing their webpage at http://www.shrewsbury.gov.uk/public/yourcouncilatwork/housing/advice/default.htm
Quick Links:
Location
Whitehouse Gardens, Ditherington.
You can click on the map to open a moveable map.
Please note that drawings posted on our Council Projects website are not definitive and for illustrative purposes only. No such drawings will supersede the planning drawings without consent from the planning authority unless any change is not deemed to be subject to the afore mentioned procedures.
Current Use
This is the site of the old community centre which fell into disrepair and was eventually demolished by SABC due to its poor structural condition. The site was then cleared and maintained as a grassed area by SABC.
Proposed Use
This site was identified as suitable for six 3 bed semi detached homes. Planning permission (05/1549/DDM) was granted in Feb 2006 along with Building Regulation approval shortly afterwards. The development of Council land and other assets is through the Council's established procurement route in order to demonstrate best value. In this instance, a managing design team (ETC Ltd) was chosen through a tender and interview process, to handle contractually concept to completion.
Status
- October 2006 - Tenders received and evaluated
- November 2006 - Work commences on site
- January 2007 - Brickwork completed to roof level

-
February 2007 - Roof trusses in place
-
March 2007 - 1st fix commences

-
May 2007 - 2nd fix commences, portacabins removed from site.
-
June 2007 - Project completed.